How much concrete do you lose in pump truck?

2024-12-10 Visits:

  How much concrete do you lose in pump truck? The amount of concrete lost in a pump truck typically ranges from 1 to 2 cubic yard (0.76 to 1.5 cubic meters) per load, depending on several factors:

44807535-82a0-486f-b085-a73e12d295c9-1024x768.jpg

  1. Volume of Concrete Used


  For smaller jobs where less than 30 cubic yards (23 m?) of concrete is used, the percentage of concrete lost due to pump inefficiencies tends to be higher as a proportion of total volume compared to larger projects.


  2. Type of Pump Truck


  Different models of pump trucks have different capacities and efficiencies. Some newer models feature advanced cleaning systems that allow for more complete evacuation of the concrete from the lines, thus reducing wastage.


  3. Type of Pump and Hose Length


  Longer hoses or pipelines can lead to higher concrete loss due to residual material left inside after pumping.


  4. Mix Design


  High-slump or flowable concrete leaves less residue in the pump and hoses compared to low-slump or stiff mixes.


  5. Cleanout Method


  The cleanout process affects the loss. Using water to flush the system minimizes waste, while mechanical cleaning can result in more leftover material.


  6. Project Size


  Smaller pours tend to lose a larger percentage of concrete, as the pump system requires a certain volume to operate effectively.


  7. Operator Skill and Experience:


  Skilled operators may be able to manage the pumping process more efficiently, minimizing the amount of concrete left in the lines.


  Minimizing Concrete Loss:


  - Use priming agents to reduce adhesion in the hoses.


  - Plan pours efficiently to minimize leftover material.


  - Reuse residual concrete for non-critical applications when possible.


  Understanding these variables helps in better estimating the potential loss and managing expectations regarding the final volume of concrete delivered versus what actually reaches the pour site. It's advisable for project managers to factor in this potential loss when calculating their requirements to ensure they order sufficient concrete without causing unnecessary expense through underestimation.